PROJECT UPDATE as of Friday, June 10, 2022
UPDATE AS OF FRIDAY, JUNE 10, 2022: Night work has concluded for the N Delphine Ave Stormwater project. Due to weather and field conditions the project timeline is extended into the week of June 13th during the hours of 7:00am – 5:00pm. There will be two lane traffic in an altered pattern during the remainder of the project.
PROJECT UPDATE as of Wednesday, June 8, 2022
UPDATE AS OF WEDNESDAY, JUNE 8, 2022: Phase I of the drainage project on N. Delphine Avenue is progressing according to schedule, weather permitting. Please take precaution in this area through June 10th.
Phase I of Drainage Project Scheduled to Begin on Monday, June 6th
Phase I of a drainage improvement project will begin on Monday, June 6 at the 1500 block of N Delphine Ave.
Will there be any traffic delays?
Traffic will be reduced to one lane from 7pm – 8am for a period of one week.
Could the project dates be changed because of weather?
The dates may change with a threat of inclement weather. Please take precaution in this area from June 6 – 10.